Building Durable Longitudinal Joints
INTRODUCTION
One of the most common failure modes of asphalt pavements occurs along the cold joint that is constructed between adjacent lanes of paving. All too often raveling occurs along the joint, most often on the side where the second lane was paved. This is usually a result of inadequate compaction of the longitudinal joint. Poor compaction in this area leads to a more permeable mix that allows water to penetrate the joint and weaken the bond between the asphalt cement and aggregate. Eventually, the bond becomes weak enough that aggregate begins to dislodge from the joint resulting in raveling and eventual failure of the pavement. There are several construction practices that can be employed to ensure a well-compacted longitudinal joint that will not fail prematurely. The construction practices used to build a durable joint cost no more than those used to construct a poor joint.
WHAT IS REQUIRED TO ENSURE A DURABLE LONGITUDINAL JOINT?
There are four primary factors that the paving crew must consider when constructing the longitudinal joint. They are:
1. COMPACTION OF THE UNSUPPORTED EDGE OF THE FIRST LANE PLACED
As soon as the first lane is placed, the breakdown roller should make the first pass on the low side of the mat with the steel drum overhanging about six inches. The second pass should be made on the opposite side of the mat, again overhanging the steel drum about six inches. This technique of overhanging eliminates transverse shear loading near the edge of the mat and forces the mix vertically downward instead of pushing it sideways and out.
2. OVERLAP OF MIX FROM SECOND LANE PAVED ONTO THE FIRST LANE
The second practice to constructing a durable longitudinal joint is the overlap of mix from the second lane onto the first lane. There are two things to know in this situation. First, when the loose mix from lane 2 is placed over top of the compacted mix of lane 1, the mix should be high by the amount of compaction that will occur. Dense-graded mixes will compact approximately ¼″ per inch of mix laid. In other words, for every one inch of desired mat thickness after compaction, approximately 1 ¼″ of loose mix should be placed behind the paver. If a two-inch final lift thickness is desired, 2 ½″ of loose mix should be placed behind the paver. This “fluff factor,” as it is often called, will vary slightly depending on the mix being used and the thickness of the lift being placed. After a few truckloads, the paving crew will be able to fine-tune the fluff factor to place the exact amount of loose mix that will result in the desired mat thickness after compaction.
The second consideration is the amount of overlap of the second lane placed onto the first lane. If too much overlap occurs, the excess mix will have to be raked away from the joint. If not enough mix is placed at the joint; a depression or invert will occur on the lane 2 side of the joint and collect water when it rains. In general, the amount of overlap required is in the range of 1 to 1 ½″ when using a ¾″ inch mix down to as little as ¼″ of overlap when using a half-inch mix. With careful attention to the amount of overlap, little or no raking of the mix at the joint is necessary.
3. RAKING AT THE LONGITUDINAL JOINT
If the proper amount of overlap is placed at the longitudinal joint, no raking is necessary. Some raking may be required when a ¾″ mix is used and the lift thickness is less than 4 inches. In this case, only the coarse aggregate sitting on lane 1 that could be crushed by the rollers should be raked away from the joint and properly disposed of off the roadway. Excess mix at the joint should not be broadcast back onto the surface of lane 2. When mix is broadcast back onto the mat, the coarse aggregate gets rolled into the surface without any fines surrounding it. Water will collect around the coarse aggregate, seep into the pavement and enable the onset of raveling. Also, when mix is raked away from the joint, there is not enough mix remaining at the joint to achieve maximum density after the rollers compress it. Finally, the joint should not be raked flat. Since the new mix being placed must be ¼″ per inch high, raking flat will leave no mix to be compacted since it will already be at the same elevation as the compacted mix in lane 1 before the rollers pass over it.
4. COMPACTING THE LONGITUDINAL JOINT
The final aspect to constructing a durable longitudinal joint is the rolling pattern used. Historically, pinching the joint from the lane 1, or cold side of the joint was common practice. Research has shown that this results in lower compaction at the joint and is also inefficient from a production standpoint. When pinching from the cold side, the roller cannot be operated in vibratory mode and the majority of the hot mat is losing temperature as the roller pinches the joint. The recommended practice for compacting the longitudinal joint is to roll with the steel drum almost entirely on the hot mat, overlapping onto the cold mat by about 6 inches. Using this procedure is much more efficient as the entire width of the steel drum is being utilized in vibratory mode while the mix is still hot.
SUMMARY
There are four primary considerations for constructing a durable longitudinal joint.
Although there are variations to the methods outlined in this paper that have been successful, the procedures described here are the most effective and efficient in almost all situations. The most successful way to fine-tune your practices for building longitudinal joints is to try different techniques, document what you do, and get measured feedback from core density data.1
Reference: Scherocman, J.A., “Construction of Durable Longitudinal Joints,” August 2002.
One of the most common failure modes of asphalt pavements occurs along the cold joint that is constructed between adjacent lanes of paving. All too often raveling occurs along the joint, most often on the side where the second lane was paved. This is usually a result of inadequate compaction of the longitudinal joint. Poor compaction in this area leads to a more permeable mix that allows water to penetrate the joint and weaken the bond between the asphalt cement and aggregate. Eventually, the bond becomes weak enough that aggregate begins to dislodge from the joint resulting in raveling and eventual failure of the pavement. There are several construction practices that can be employed to ensure a well-compacted longitudinal joint that will not fail prematurely. The construction practices used to build a durable joint cost no more than those used to construct a poor joint.
WHAT IS REQUIRED TO ENSURE A DURABLE LONGITUDINAL JOINT?
There are four primary factors that the paving crew must consider when constructing the longitudinal joint. They are:
- Compaction of the unsupported edge of the first lane paved.
- Overlap of the second lane paved onto the first lane.
- Raking mix along the joint.
- Compaction of the joint between the two lanes.
- The following sections will describe each factor in detail.
1. COMPACTION OF THE UNSUPPORTED EDGE OF THE FIRST LANE PLACED
As soon as the first lane is placed, the breakdown roller should make the first pass on the low side of the mat with the steel drum overhanging about six inches. The second pass should be made on the opposite side of the mat, again overhanging the steel drum about six inches. This technique of overhanging eliminates transverse shear loading near the edge of the mat and forces the mix vertically downward instead of pushing it sideways and out.
2. OVERLAP OF MIX FROM SECOND LANE PAVED ONTO THE FIRST LANE
The second practice to constructing a durable longitudinal joint is the overlap of mix from the second lane onto the first lane. There are two things to know in this situation. First, when the loose mix from lane 2 is placed over top of the compacted mix of lane 1, the mix should be high by the amount of compaction that will occur. Dense-graded mixes will compact approximately ¼″ per inch of mix laid. In other words, for every one inch of desired mat thickness after compaction, approximately 1 ¼″ of loose mix should be placed behind the paver. If a two-inch final lift thickness is desired, 2 ½″ of loose mix should be placed behind the paver. This “fluff factor,” as it is often called, will vary slightly depending on the mix being used and the thickness of the lift being placed. After a few truckloads, the paving crew will be able to fine-tune the fluff factor to place the exact amount of loose mix that will result in the desired mat thickness after compaction.
The second consideration is the amount of overlap of the second lane placed onto the first lane. If too much overlap occurs, the excess mix will have to be raked away from the joint. If not enough mix is placed at the joint; a depression or invert will occur on the lane 2 side of the joint and collect water when it rains. In general, the amount of overlap required is in the range of 1 to 1 ½″ when using a ¾″ inch mix down to as little as ¼″ of overlap when using a half-inch mix. With careful attention to the amount of overlap, little or no raking of the mix at the joint is necessary.
3. RAKING AT THE LONGITUDINAL JOINT
If the proper amount of overlap is placed at the longitudinal joint, no raking is necessary. Some raking may be required when a ¾″ mix is used and the lift thickness is less than 4 inches. In this case, only the coarse aggregate sitting on lane 1 that could be crushed by the rollers should be raked away from the joint and properly disposed of off the roadway. Excess mix at the joint should not be broadcast back onto the surface of lane 2. When mix is broadcast back onto the mat, the coarse aggregate gets rolled into the surface without any fines surrounding it. Water will collect around the coarse aggregate, seep into the pavement and enable the onset of raveling. Also, when mix is raked away from the joint, there is not enough mix remaining at the joint to achieve maximum density after the rollers compress it. Finally, the joint should not be raked flat. Since the new mix being placed must be ¼″ per inch high, raking flat will leave no mix to be compacted since it will already be at the same elevation as the compacted mix in lane 1 before the rollers pass over it.
4. COMPACTING THE LONGITUDINAL JOINT
The final aspect to constructing a durable longitudinal joint is the rolling pattern used. Historically, pinching the joint from the lane 1, or cold side of the joint was common practice. Research has shown that this results in lower compaction at the joint and is also inefficient from a production standpoint. When pinching from the cold side, the roller cannot be operated in vibratory mode and the majority of the hot mat is losing temperature as the roller pinches the joint. The recommended practice for compacting the longitudinal joint is to roll with the steel drum almost entirely on the hot mat, overlapping onto the cold mat by about 6 inches. Using this procedure is much more efficient as the entire width of the steel drum is being utilized in vibratory mode while the mix is still hot.
SUMMARY
There are four primary considerations for constructing a durable longitudinal joint.
- Compaction of the unsupported edge of the first lane placed.Overhang the steel drum about 6″ over the unsupported edge of the first lane placed.
- Overlap of the second lane onto the first lane.Minimize the amount of overlap from lane 2 onto lane 1, but ensure sufficient material so that the compacted lane 2 matches the lane 1 elevation.
- Raking the joint.Use minimal to no raking. This will depend entirely on how well the overlap is managed by the screed operator. Do not broadcast excess mix across the mat; pull it off the mat and dispose of it off the roadway.
- Compaction of the mix at the joint.Compact the mix from the hot side of the joint using vibratory mode. Overlap the steel drum approximately 6″ onto the cold mat (lane 1).
Although there are variations to the methods outlined in this paper that have been successful, the procedures described here are the most effective and efficient in almost all situations. The most successful way to fine-tune your practices for building longitudinal joints is to try different techniques, document what you do, and get measured feedback from core density data.1
- Due to the geometry of the longitudinal joint where two lanes meet, the location of where cores are centered on the joint can have a significant impact on the compaction results obtained. Core location is beyond the scope of this article. Please contact Graniterock if you would like more information regarding optimal core location.
Reference: Scherocman, J.A., “Construction of Durable Longitudinal Joints,” August 2002.